Skip to content
Solar PV

BIS Guidelines for the Revised QCO for Power Inverters for PV Systems (March 2025)

How power inverters for PV systems add IS/IEC 61683:1999 efficiency testing to IS 16221 (Part 2) under MNRE's 2025 order, with declared efficiency for every model.

Issued byBureau of Indian Standards, Registration Department
ReferenceRegistration/ Power Invertors for use in Photovoltaic Power Systems
Edition26 March 2025
Length10 pages, PDF
StatusThe 27 July 2025 cut-off has passed, so no new licence for PV power inverters is granted without an IS/IEC 61683:1999 report.
Official copycrsbis.in
Our copyDownload PDF, saved from the official source

What this document is

On 27 January 2025 MNRE issued the Solar Systems, Devices and Components Goods Order, 2025 (S.O. 492(E)). It replaces the 2017 solar CRS order and took effect on 27 July 2025. For power inverters for use in PV power systems it adds a second standard, IS/IEC 61683:1999, on top of the safety standard IS 16221 (Part 2):2015.

On 26 March 2025 the BIS Registration Department issued this guideline (reference Registration/ Power Invertors for use in Photovoltaic Power Systems). The PDF is 10 pages, most of which is a copy of the gazette order.

Solar goods come under MNRE’s order, not MeitY’s. MeitY’s CRS FAQs and its series guidelines do not apply. Lead models are chosen under MNRE’s own series guidelines of 26 August 2019.

What changed

  • IS/IEC 61683:1999 (procedure for measuring the efficiency of power conditioners) now applies to this product.
  • The maker declares the efficiency of every model, lead and series, and BIS checks it against the test report.
  • The standard mark now shows IS 16221 (Part 2)/IEC 62109-2 and IS/IEC 61683 with the R-number.

Key dates

  • 27 July 2025: the date the order took effect. New applications and inclusions without an IS/IEC 61683 report were processed only until this date, against a declaration to comply later.
  • After 27 July 2025: no new licence without compliance with the new order.
  • Existing licensees implement within the timeline in the order, which keeps existing licences valid and brings renewals after expiry under the new order.

Existing licensees

  1. Apply through the Standard Revision/Amendment/Essential Requirement module with an IS/IEC 61683:1999 report for each lead model. Each report names the series models it covers.
  2. Declare the efficiency of every model in the licence.
  3. Pay the extension-of-scope fee (see the FAQs below).
  4. BIS issues a letter listing the compliant models. Models without an IS/IEC 61683 report are deleted after the deadline, and a licence with no compliant models is liable to expire.

New applicants and changes in scope

New applications and inclusions need reports to IS 16221 (Part 2):2015 and IS/IEC 61683:1999, with a declared efficiency for every model. Existing licensees must not use the Inclusion module to add IS/IEC 61683 to registered models.

Status

The cut-off has passed and IS/IEC 61683 applies to all solar inverters and power converters registered under this item. Utility-interconnected inverters are a separate item with their own guideline, for IS 16169:2019 and IS 17980:2022.

Products this document applies to

Each product page shows the Indian Standard, the notifying order and how to register.

About IS 16221 and its BIS labs

Frequently asked questions

Which standards apply to power inverters for PV systems under the 2025 order?

IS 16221 (Part 2):2015 for safety, as before, and IS/IEC 61683:1999 for measuring efficiency, which the 2025 order added. Both appear in the standard mark with the R-number.

What does IS/IEC 61683 cover?

It sets out how to measure the efficiency of power conditioners in stand-alone and utility-interactive PV systems whose output is a stable AC voltage at constant frequency or a stable DC voltage. The maker declares the efficiency of each model and BIS checks it against the test report.

What does it cost an existing licensee to add IS/IEC 61683?

The extension-of-scope fee under the Conformity Assessment Regulations, 2018: Rs 30,000 plus taxes per application, which covers one test report, and Rs 20,000 plus taxes for each additional report.

More in Solar PV

Also on our CRS guidelines page: Series guidelines · CRS FAQs · IS/IEC 62368-1:2023 migration · Product standards

All CRS guidelines and FAQs

Related guides from our team

This page is our summary of an official document, written for general guidance. The PDF is the authoritative text. BIS and MeitY revise these documents from time to time, so check the official source or speak to our team before acting. Published 26 March 2025.

Planning a CRS registration?

We group your models, choose the lead models and file on the CRS portal, so testing runs once.

Call WhatsApp Get a quote