BIS Guidelines for the Revised QCO for Solar PV Modules (March 2025)

How crystalline and thin-film PV modules move to IS 14286 (Part 1):2023 and IS/IEC 61730:2016 under MNRE's 2025 order, with a minimum efficiency for grant of licence.

Issued byBureau of Indian Standards, Registration Department
ReferenceReg/Solar PV Modules
Edition27 March 2025
Length13 pages, PDF
StatusThe 27 July 2025 cut-off has passed, so no new PV module licence is granted without the revised standards; the IS/IEC 61730 parts are now moving to their 2023 editions by 15 February 2027.
Official copycrsbis.in
Our copyDownload PDF, saved from the official source

What this document is

On 27 January 2025 the Ministry of New and Renewable Energy (MNRE) issued the Solar Systems, Devices and Components Goods Order, 2025 (S.O. 492(E)). It replaces the Solar Photovoltaics, Systems, Devices and Components Goods (Requirements for Compulsory Registration) Order, 2017 and came into force 180 days after publication.

On 27 March 2025 the BIS Registration Department issued this guideline (reference Reg/Solar PV Modules) on how module makers move to the revised standards. The PDF runs to 13 pages, including the annexure of changes and a copy of the gazette order.

Solar goods come under MNRE’s order, not MeitY’s. MeitY’s CRS FAQs and its series guidelines do not apply to them.

What changed

ProductOld standardsNew standards
Crystalline silicon PV modulesIS 14286:2010, IS/IEC 61730-1 and -2:2004IS 14286 (Part 1):2023 and (Part 1/Sec 1):2023, IS/IEC 61730-1 and -2:2016
Thin-film PV modulesIS 16077:2013, IS/IEC 61730-1 and -2:2004IS 14286 (Part 1):2023 with Sec 2 (CdTe), Sec 3 (a-Si) or Sec 4 (CIGS), IS/IEC 61730-1 and -2:2016

The order also sets a minimum efficiency at standard test conditions for grant of licence: 18% for monocrystalline and thin-film modules, 17% for polycrystalline modules. Laboratories report the maximum output, module area and calculated efficiency in the test report.

The annexure lists the main technical changes. IS 14286 now has a general Part 1, technology sections and a Part 2 of test methods. Pass/fail is split into two “gates”, and new tests include potential-induced degradation, cyclic mechanical load and bending for flexible modules, with rules for bifacial modules. The 2016 editions of IS/IEC 61730 add insulation coordination, component qualification for junction boxes, cables and connectors, and new tests such as sharp edge, ignitability and peel tests.

Key dates

  • 27 July 2025: the date the 2025 order took effect. Applications and inclusions under the old standards were processed only until this date.
  • After 27 July 2025: no new licence for PV modules without compliance with the new order.
  • Existing licensees implement within the timeline in the order. The order keeps existing licences valid and brings renewals after expiry under the new order.

Existing licensees

  1. Group all existing models and pick representative models under clause 4 of IS 14286 (Part 1).
  2. Get complete tests on the representative models to the applicable IS 14286 section and IS/IEC 61730-1 and -2:2016. Series models and extra bills of materials get the retests set out in IS/IEC TS 62915.
  3. Apply through the Standard Revision/Amendment/Essential Requirement module with the third-party test reports. New models go through the Inclusion module.
  4. BIS issues a letter listing the compliant models. Models still on the old standards are deleted after the deadline, and a licence with no compliant models is liable to expire.

New applicants and changes in scope

  • New applications and inclusions need reports to the applicable IS 14286 section and IS/IEC 61730-1 and -2:2016.
  • A series model cannot be added under the new standards until the representative model has moved over.
  • Existing licensees must not use the Inclusion module to update registered models.

Status

The cut-off dates in this guideline have passed. IS/IEC 61730-1 and -2 have since been revised again. BIS’s transition guideline for IS/IEC 61730:2023 of 30 December 2025 sets out partial testing for modules already on the 2016 editions, with concurrent running until 15 February 2027.

Products this document applies to

Each product page shows the Indian Standard, the notifying order and how to register.

About IS 14286 and its BIS labsAbout IS 16077 and its BIS labsAbout IS/IEC 61730 and its BIS labs

Frequently asked questions

Which standards apply to solar PV modules under the 2025 order?

IS 14286 (Part 1):2023 for general requirements, plus the section for the technology: Section 1 for crystalline silicon, and Sections 2, 3 or 4 for CdTe, amorphous silicon or CIGS thin-film modules. IS/IEC 61730-1 and 61730-2 cover safety. IS 16077:2013 for thin-film modules and the 2010 and 2004 editions are replaced.

Is there a minimum efficiency for BIS registration of solar panels?

Yes. The 2025 order sets a minimum efficiency at standard test conditions for grant of licence: 18% for monocrystalline and thin-film modules and 17% for polycrystalline modules. The laboratory reports the maximum output, module area and calculated efficiency in the test report.

How are models grouped for testing under the revised standards?

Series are formed under clause 4 of IS 14286 (Part 1), and changes in the bill of materials are handled by retesting under IS/IEC TS 62915. Representative models get complete testing and series models get the applicable retests.

More in Solar PV

Also on our CRS guidelines page: Series guidelines · CRS FAQs · IS/IEC 62368-1:2023 migration · Product standards

All CRS guidelines and FAQs

Related guides from our team

This page is our summary of an official document, written for general guidance. The PDF is the authoritative text. BIS and MeitY revise these documents from time to time, so check the official source or speak to our team before acting. Published 27 March 2025.

Planning a CRS registration?

We group your models, choose the lead models and file on the CRS portal, so testing runs once.

Call WhatsApp Get a quote