IS 16169 BIS Certification for Grid-Tied Solar Inverters
Grid-Tied Solar Inverters made, imported or sold in India must be certified against IS 16169 under CRS registration (Scheme-II). What the standard covers, how testing works and how to get the registration.
About IS 16169
| Standard | IS 16169 |
|---|---|
| Title | Test Procedure of Islanding Prevention Measures for Utility-Interconnected Photovoltaic Inverters |
| Product covered | Grid-Tied Solar Inverters |
| Category | Solar PV Systems & Components |
| Scheme | CRS registration (Scheme-II) |
| Notified under | Solar Systems, Devices and Components Goods Order, 2025, S.O. 492(E), dated 27 January 2025 · Order PDF |
Editions and amendments of IS 16169
| Edition | Published | Status |
|---|---|---|
| IS 16169:2019 Utility - Interconnected photovoltaic inverters - Test procedure of islanding prevention measures (First Revision) | 30 Jun 2019 | Current, next review 26 Feb 2031 |
| IS 16169:2014 Utility - Interconnected photovoltaic inverters - Test procedure of islanding prevention measures | 30 Jun 2019 | Withdrawn 21 Feb 2026 |
No amendments to the current edition are listed by BIS.
Testing against IS 16169
Samples are type-tested at a BIS-recognised laboratory in India; foreign lab reports are not accepted. BIS then reviews the test report and documents and grants the registration. Market surveillance samples follow.
The test report has to cover every clause of IS 16169 that applies to the product, in the edition current on the date of testing. When BIS revises IS 16169 or replaces it with a new edition, existing licence holders move to the new edition by the date BIS sets in its notification.
Official guidelines for IS 16169
Official BIS documents with the rules and deadlines for registering products to this standard under CRS.
- BIS Guidelines for the Revised QCO for Utility-Interconnected PV Inverters (March 2025)How utility-interconnected PV inverters move to IS 16169:2019 for anti-islanding and add IS 17980:2022 MPPT efficiency tests under MNRE's 2025 order.
- MNRE Series Guidelines for Solar PV Inverters (2019, and 2025 Draft)How off-grid, grid-tied and hybrid solar inverters are grouped into families with the same hardware and firmware, so the highest-rated model's safety tests cover the rest.
How to get CRS registration under IS 16169
Registration is granted to the manufacturer for a specific factory, brand and models. Overseas manufacturers must appoint an Authorised Indian Representative to apply and hold the registration in India.
- Confirm the Indian Standard and group models into a series
- Submit samples to a BIS-recognised lab in India for testing
- Apply on the CRS portal with the test report, factory and brand documents
- BIS review and grant of the R-number registration
- Mark products with the Standard Mark, IS number and R-number
Timeline. Lab testing usually takes 2 to 6 weeks; BIS processing typically takes another 3 to 6 weeks after a complete application with the test report.
Fees. Application and annual licence fees of ₹1,000 each, a processing fee of ₹25,000 per year, and ₹20,000 for each additional test report, plus lab testing charges (BIS Conformity Assessment Amendment Regulations, 2026).
Mark. Certified products carry the BIS Standard Mark (CRS) with the IS number and the R-number.
Frequently asked questions
What does IS 16169 cover?
IS 16169: Test Procedure of Islanding Prevention Measures for Utility-Interconnected Photovoltaic Inverters. BIS has made certification against it compulsory for grid-tied solar inverters.
Is BIS certification under IS 16169 mandatory?
Yes, for grid-tied solar inverters, under the Solar Systems, Devices and Components Goods Order, 2025, S.O. 492(E). The product needs a valid BIS registration (CRS) and must carry the BIS Standard Mark (CRS) with the IS number and the R-number.
Where is a product tested for IS 16169?
Samples are type-tested at a BIS-recognised laboratory in India; foreign lab reports are not accepted. BIS then reviews the test report and documents and grants the registration. Market surveillance samples follow.
How long does IS 16169 BIS certification take?
Lab testing usually takes 2 to 6 weeks; BIS processing typically takes another 3 to 6 weeks after a complete application with the test report.
Other standards in Solar PV Systems & Components
- IS 14286 2 products
- IS 16221 2 products
- IS 16270 Solar Storage Batteries
- IS 17980 Grid-Tied Solar Inverters
- IS/IEC 61683 Solar Inverters and Power Converters
- IS/IEC 61730 2 products
Source: BIS lists of products under compulsory certification (Scheme-I, Scheme-II, Scheme-IV), checked November 2026. See the full BIS product list or all Indian Standards.
Not sure which certification your product needs?
Talk to a team led by former BIS Directors. We'll map every approval your product needs before you spend on testing.