Skip to content
Solar PV

MNRE Series Guidelines for Solar PV Inverters (2019, and 2025 Draft)

How off-grid, grid-tied and hybrid solar inverters are grouped into families with the same hardware and firmware, so the highest-rated model's safety tests cover the rest.

Issued byMinistry of New and Renewable Energy (MNRE), Standards and Quality Control Division
ReferenceFile No. 223/36/2018-R & D Coord (QC)
Edition26 August 2019
Length6 pages, PDF
StatusIn use: BIS's March 2025 guidelines for the 2025 solar order ask for test reports for each lead model under these guidelines. MNRE circulated revised guidelines as a draft for comments on 23 June 2025, and we have not found a final version.
Official copycdnbbsr.s3waas.gov.in
Our copyDownload PDF, saved from the official source

What this document is

Solar inverters are registered with BIS under MNRE’s Solar Systems, Devices and Components Goods Order, 2025 (S.O. 492(E)), which replaced the 2017 order. MeitY’s CRS series guidelines do not apply to them. MNRE’s Standards and Quality Control Division issued these guidelines on 26 August 2019 (File No. 223/36/2018-R & D Coord (QC)) so that laboratories and manufacturers could group inverters into families, with one model tested for the whole family.

They were written for the 2017 order, but BIS’s guidelines of 26 March 2025 for PV power inverters and grid-tied inverters under the 2025 order still ask for test reports for each lead model “as per MNRE’s series guidelines dated 26th August 2019”.

Scope

  • Off-grid, grid-tied and hybrid solar PV inverters of up to 150 kW.
  • PV input rated up to 1000 or 1100 V DC, and AC output of 415 V nominal. Inverters rated 1100 V DC are tested at 1000 V.
  • Inverters rated above 1000 V DC and above 415 V AC are not covered.

What one family must share

A product family is defined by the maximum configuration of components and sub-assemblies, plus how each model is built from it. The models in a family must have:

  • the same hardware and firmware, as declared by the manufacturer. Firmware limit settings can differ with each model’s rating, but its overall functionality must be the same;
  • the same rated input and output voltage, output frequency and number of output phases;
  • the same PCB design and layout, and the same power stage topology;
  • the same insulation class: low frequency transformer, high frequency transformer or transformerless;
  • the same control algorithm, cabinet design and class of construction.

Components with different power or current ratings are allowed within a family, provided the inverter with the maximum rated components (EMC filters, capacitors, transformers, inductors, IGBTs or MOSFETs) is tested. Models with a different hardware architecture or firmware functionality are tested separately. If only the cabinet design changes, every cabinet design is tested or verified for ingress protection, at a NABL laboratory or from ISO/IEC 17025 or ILAC-accredited test reports.

How the family is tested

  1. The manufacturer declares the series when submitting samples.
  2. Two samples of the maximum rated model go to the laboratory, and one is tested to IS 16221 (Part 2), which brings in the tests of IS 16221 (Part 1), and to IS 16169 for anti-islanding. IS 16169 is not tested for standalone or off-grid inverters.
  3. The lab charges only for the highest-rated model, and issues the test report to all the lower-rated models, with each model’s product label in it.
  4. Any change in construction, materials or components within the family means fresh testing.

Retests. Testing runs in two sequences. If a test fails, a new sample is submitted and only that sequence is repeated, after a review of components and construction. Each sequence allows one failure, and a second failure in the same sequence counts as a total failure. Repeat IS 16169 tests cover three balanced and any two imbalanced conditions.

Brands and factories. All brands and their model numbers are listed in the test report with their product labels, and samples of each brand are not needed. Products made in two different locations are tested separately.

Documents to send with the samples

The laboratory should not accept inverters without:

  1. Product datasheet.
  2. Complete bill of materials.
  3. Safety certificates to IEC or equivalent standards for critical components.
  4. Schematic or single line diagram with the working principle.
  5. Enclosure opening drawings.
  6. PCB wiring diagrams and layouts with voltage markings and component layouts.
  7. Bare PCBs for spacing measurements, and one extra set of populated PCBs for destructive safety tests.
  8. User, instruction or operation manual.
  9. Any internal test reports.
  10. Mounting and grounding hardware, and a spare cable with connectors, one end open.
  11. Firmware details such as the version name.

Inverters are marked under clause 5 of IS 16221 (Part 2) with the maker’s name or trade mark, the model, a serial number or code that identifies the factory and a three-month production window, input and output ratings, and the IP rating.

The June 2025 draft

On 23 June 2025 MNRE circulated draft series guidelines for SPV inverters under the 2025 order, with comments due within 15 days. The family rules, documents, retests and brand rules are largely the same. The main changes:

  • No capacity or voltage limits. The draft applies to off-grid, grid-tied and hybrid inverters, without the 150 kW, 1000 V DC and 415 V AC limits.
  • Efficiency tested model by model. The highest-rated model still covers the family for IS 16221 (Part 2):2015 and IS 16169:2019, but every model is tested separately to IS/IEC 61683:1999 and IS 17980:2022, because efficiency varies from model to model. Fees and test reports for these two standards are per model.

Download the June 2025 draft (7 pages, scanned, official copy). We have not found a final version, so the 2019 guidelines remain the ones BIS cites.

Status

BIS applies these guidelines to lead models under the 2025 order. If you are grouping inverters now, check with the laboratory whether it is following the 2019 text or the June 2025 draft for efficiency testing. Solar batteries have their own MNRE series guidelines, and the solar BIS guide covers each product’s standards.

Products this document applies to

Each product page shows the Indian Standard, the notifying order and how to register.

About IS 16221 and its BIS labsAbout IS 16169 and its BIS labs

Frequently asked questions

What must inverters in one family have in common?

The same hardware and firmware, rated input and output voltage, output frequency and number of phases, PCB design and layout, power stage topology, insulation class (low or high frequency transformer, or transformerless), control algorithm and cabinet design. Firmware limit settings can differ with the model's rating.

Which inverter in a family is tested?

The maximum rated model. The manufacturer sends two samples of it and one is tested. The lab charges only for that model and issues the test report to all the lower-rated models in the family, with each model's product label in the report.

Do different brands or factories need separate tests?

Brands do not: all brands and model numbers are listed in the test report, with their labels, and samples of each brand are not needed. Factories do: products made in two different locations are tested separately.

Do efficiency tests also go by family?

Under BIS's March 2025 guidelines, IS/IEC 61683 and IS 17980 reports are submitted for each lead model and the maker declares the efficiency of every model. MNRE's June 2025 draft would have every model tested separately for these two standards, because efficiency varies from model to model.

More in Solar PV

Also on our CRS guidelines page: Series guidelines · CRS FAQs · IS/IEC 62368-1:2023 migration · Product standards

All CRS guidelines and FAQs

Related guides from our team

This page is our summary of an official document, written for general guidance. The PDF is the authoritative text. BIS and MeitY revise these documents from time to time, so check the official source or speak to our team before acting. Published 26 August 2019.

Planning a CRS registration?

We group your models, choose the lead models and file on the CRS portal, so testing runs once.

Call WhatsApp Get a quote